know How to Repair Reinforced concrete Old slabs with the bottom falling off due to steel corrosion and New Reinforced Slabs with bottom plaster falling off due to lack of bond
There are many cases where the part below the steel layer
of the RC roof or floor slab has collapsed. We can divide the reasons for this
failure into two headings.
Case 1: Is the falling off the
bottom of the slab after many years due to corrosion of steel.
Case 2: Is that of the bottom
layer falling off soon after plastering during the construction of the slab due
to lack of bond.
In this article, we explain the repair of these two cases.
Case 1: Old Slabs with the Bottom Falling Off Due to Steel Corrosion
Corrosion of steel and cracking of the underside of older
RC roofs is very common. Usually, in the case of roof slabs and slabs under the
bathroom, corrosion of steel occurs due to leakage and water seepage. The RC
slab below fig shows corroded steel below. When this occurs in other
intermediate floor layers, the steel corrosion can be determined by a
phenolphthalein test. Then it can happen again. Also, old twisted high-yield
bars (Tor steel) usually rust faster compared to modern hot-rolled high-strength steel bars. So, if we add any steel, let it be hot rolled bars. Before
starting work, prop the RC slab in some places. It's good to support.
Figure: RC slab with bottom steel corroded.
The main method of repair is to first remove and clean the
loose concrete, clean the steel bars, and apply a bonding coat to clear the
steel and concrete. We then apply micro concrete made of cement, sand, and
small-size coarse aggregates (below 10 mm) along with superplasticizers or
polymers to make the concrete workable. We may add additional steel if the
corrosion has consumed a lot of steel, say more than 15%. This is done by spot
welding the new steel to the old steel or by clamping to concrete.
For filling up the gaps in the concrete, we use less costly
plasticizers for large areas and in the case of small areas, we may use more costly
and efficient polymer-modified cement and mortar or concrete.
Procedure for repairing the
corroded slab by the following steps:
Step 1: Support the slab with props to relieve some load from the
slab.
Step 2: Remove all the
defective concrete and expose the corroded reinforcement to its full
circumference. A clear gap of 15 mm below the steel is recommended by CPWD. As
the slab is supported, it becomes more stable.
Step 3: If possible, conduct a carbonation test to find the
depth of concrete up to which the carbonation has occurred. Remove concrete
from that depth.
Step 4: Clean the
reinforcement thoroughly and add extra reinforcement, if required, by using U
clamps or by welding it to the old reinforcement.
Step 5: Thoroughly clean the concrete surface.
Step 6: Apply an anticorrosive protective passivating coat to all
the steel including ties.
Step 7: Apply the bonding coat to the old concrete surface also.
Step 8: Apply polymer-modified mortar, as it needs less curing
and attains very good strength. This should be applied before the bond coat
gets dry
Step 9: Water cure for 7 days by brushing with water or other
means.
Step 10: Painting with cement paint or carbonation-resistant paint,
if needed, can be carried out after the surface gets dry.
Figure: Repair scheme showing applications of (a) corrosion
inhibiting cum bond coat, (b) polymer modified repair mortar, and (c)
carbonation resistance flexible coating.
Case 2: Falling Off of Bottom Plaster of New RC Slabs Due to Lack of Bond
The bottom falling off new RC slab plastering is mainly due
to a lack of bond between the finishing plaster and the concrete. Another major
reason is the lack of proper notching or hacking at the base of the slab as per
standard practice. As today's cement with high ash content gives a very smooth
surface when finished, it is essential to strictly follow the old hacking practice
or use modern construction chemicals to bond concrete surfaces.
The old specification called for hacking with a sharp tool
so that the depression was not less than 3 mm deep and spaced not more than 50
mm apart. Nowadays, it is difficult to get hackers, thus, plastering under the
slab is reduced due to the lack of bond.
In such cases, the solution is to use modern construction
chemicals. We must first apply a bond coat of polymer latex or cement polymer-modified cement slurry, then, before the bond coat dries, plaster is applied
with polymer-modified 1:3 cement sand mortar as specified by the manufacturers
of chemicals. Water purification should be carried out for at least seven days,
after which the desired painting can be carried out on the surface.
Conclusion:
RC slab affected by corrosion
of steel reinforcement can now be successfully repaired using concrete
chemicals. If you dry out the repaired slab and keep out the main enemy,
moisture, it will look good for a very long time. The use of bonding chemicals
can prevent plastering from falling off the bottom of newly constructed slabs
due to a lack of bond with the concrete slab.
No comments:
Post a Comment