What is the cost of brick wall construction per sqft, sqm, cft and cum?

What is the cost of brick wall construction per square foot? | What will be the cost of 9" brick wall masonry? | Rate analysis of 9" thick brick wall work. | Cost of brick wall construction per square feet (sqft) | Cost of brick wall construction per square meter (sqm) | Cost of brick wall construction per cubic feet (cft)


In this article we explained about Cost of brick wall construction per square feet (sqft), square meter (sqm), cubic feet (cft) and cubic meter (cum) 

cost of brick wall construction per square foot




Cost of brick wall construction per square feet (sqft)

 

We will consider data as to have 100 sqft brickwork

Length of the brick wall (L) = 10’ feet.

Height of the brick wall (h) = 10’ feet.

Thickness of the brick wall (w) = 9" = 0.75ft

 

Area of brick wall (sqft) = length (L) × height (H)

= 10ft. × 10ft. 

100 sq/ft.

 

Material Required Per Square Feet

Bricks needed for 1sqft brickwork = 10 nos

Cement needed for 1sqft brickwork = 1.1984 kg

Sand needed for 1sqft brickwork = 0.17556 cft

 

Must read to understand the above data: How much cement, sand, and bricks are needed for 1 sqft brickwork?

 

1. No. of Bricks required given data = (area of brick wall × bricks per sqft)

= 100sqft x 10

= 1000 nos

 

2. No. of Cement bags required given data = (area of brick wall × cement per sqft) = 100sqft x 1.1984

= 119.84kg

= 119.98 / 50

= 2.3996 – 3 bags

 

3. Volume of sand required = (area of brick wall × cement per sqft)

= 100sqft × 0.17556cft

= 17.556 cft – 18 cft

 

Labour cost required brickwork per Square Feet

Labour required for 100sqft brick wall construction

Mason – 2 nos – 2 days – 1000 INR/day – 4000

Helper – 2 nos – 2 days –850 INR/day – 1700

Total cost = 5700

Transport charges – 400

Total cost = 6100 per 100 sqft

Labour cost required brickwork per Square Feet = 6100/100 = 61 rs/sqft  

Labour cost required brickwork per Square Feet = 61 sqft (it’s the cost of a minimum 100sqft area)

 

Rate Analysis of Brick Masonry | Now, let us use the above to calculate the total cost of brick masonry per square foot in table format.



Sr No.

Description

Qty

Unit

Rate

Cost

 

Cost for Given data (100sqft)

 

 

 

 

A

Labour Charges

100

sqft

61

6100

B

Material

 

 

 

 

 

Bricks (Size of brick = 9' x 4' x3')

1000

nos

11

11000

 

5% Wastage of brick

5%

 

 

550

 

Cement

3

Bag

400

1200

 

2% Wastage of cement

2%

 

 

24

 

Sand (M-sand)

18

cft

55

990

 

2% Wastage of sand

7%

 

 

69.3

 

Cost of 100sqft brickwork

19933.3

C

Scaffolding 2% Extra

2%

 

 

398.666

D

Transportation Cost 1%

1%

 

 

199.333

E

miscellaneous Charges 2 % Extra

3%

 

 

597.999

F

Add for Water Charge @ 1% on Items Marked

1%

 

 

199.333

G

Add for Contractor’s Profit @15% on Items Marked

15%

 

 

2989.995

 

Total Cost of 100sqft brickwork

24318.626

 

 Round off sqft

25000

 

  

 

Total cost 100 sqft brick wall masonry = 25000

Total cost 1 sqft brickwall masonry = 25000/100 = 250/sqft

 

So,

The total cost of 9” brick wall construction per square foot will be 250/sqft


What is the cost of 9” brick wall construction per square foot?

The total cost of 9” brick wall construction per square foot will be 250 INR/sqft. and Labour contract cost will be 61 INR/sqft

 

What is the cost of 4.5” brick wall construction per square foot?

The total cost of 4.5” brick wall construction per square foot will be 125 INR/sqft. and Labour contract cost will be 30-32 INR/sqft

 

What is the cost of 9” brick wall construction per square meter?

We will know the cost of 9” brick wall construction per square feet is 250 INR/sqft. So, (1 sqm = 10.7639 sqft) therefore for 1 square meter 250 x 10.7639 = 2690.97 – 2700 INR sqm. Total Cost of 9” brick wall construction per square meter will be 2700 INR/sqm. and Labour contract cost will be 670 INR/sqm

 

What is the cost of 4.5” brick wall construction per square meter?

The total cost of 4.5” brick wall construction per square meter will be 1350 INR/sqm. and Labour contract cost will be 335 INR/sqm


Also read:

How much cement, sand, and bricks are needed for 1 square metre of 4.5" brickwork?

 

Thumb rule - How to calculate the number of Bricks per Square meter (m2)

 

How much cement, sand, and bricks are needed for 1 square metre of 9" brickwork?

 

Thumb rule - How many bricks are in 1 cum?

 

Thumb rule - How many bricks are in 1 CFT?

 

How Do I Calculate Brick, Sand And Cement In Brick Masonry using EXCEL?

 

How to calculate the Weight Of Bricks Per Sqm?

 

How much cement, sand, and bricks are needed for 1 cubic metre of brickwork?


How many bricks per square foot? | How many bricks in a square foot in 9" and 4.5" wall?

 

 

Cost of brick wall construction per Cubic feet (cft)


Material Required Per Cubic Feet

Bricks needed for 1 Cft brickwork = 14 nos bricks

Cement needed for 1 Cft brickwork = 1.597kg cement -  0.03194 bag

Sand needed for 1 Cft brickwork = 0.2340 cft sand

 

Must read to understand the above data: How much cement, sand, and bricks are needed for 1 cft brickwork?

 

Labour cost required brickwork per Cubic feet

We will consider the data 

Length of the brick wall (L) = 10’ feet.

Height of the brick wall (h) = 10’ feet.

Thickness of the brick wall (w) = 9" = 0.75ft

 

Volume of brick wall (sqft) = length (L) × height (H) x thickness (T)

= 10ft. × 10ft. x 0.75ft

75 Cft.

Total cost = 6100 per 100 sqft

Labour cost required brickwork per cubic Feet = 6100/75 = 81.333 = 82 inr/cft

Labour cost required brickwork per cubic Feet = 82 INR/cft

 

Rate Analysis of Brick Masonry | Now, let us use the above to calculate the total cost of brick masonry per cubic foot in table format.

 

Sr No.

Description

Qty

Unit

Rate

Cost

 

Cost for Given data (100sqft)

 

 

 

 

A

Labour Charges

1

cft

75

75

B

Material

 

 

 

 

 

Bricks (Size of brick = 9' x 4' x3')

14

nos

11

154

 

5% Wastage of brick

5%

 

 

7.7

 

Cement

0.03

Bag

400

12.776

 

2% Wastage of cement

2%

 

 

0.25552

 

Sand (M-sand)

0.23

cft

55

12.87

 

2% Wastage of sand

7%

 

 

0.9009

 

Cost of 100sqft brickwork

263.50242

C

Scaffolding 2% Extra

2%

 

 

5.2700484

D

Transportation Cost 1%

1%

 

 

2.6350242

E

miscellaneous Charges 2 % Extra

3%

 

 

7.9050726

F

Add for Water Charge @ 1% on Items Marked

1%

 

 

2.6350242

G

Add for Contractor’s Profit @15% on Items Marked

15%

 

 

39.525363

 

Total Cost of 100sqft brickwork

321.472952

 

 Round off

325

 

What is the cost of brick wall construction per cubic foot?

The total cost of brick wall construction per cubic foot will be 325 INR/cft. and Labour contract cost will be 83 INR/cft

 

What is the cost of brick wall construction per cubic meter?

The total cost of brick wall construction per cubic foot will be 11500 INR/cum. and Labour contract cost will be 2950inr/cum

 