Estimating Costs and Material Requirements for Your Home
| Guide of Home Construction Material and Cost Estimation | How do you estimate
the materials needed to build a house?
It is always worthwhile to estimate the cost of the proposed construction so that it does not exceed the available finances. We have already seen in the article “Classification of Buildings” how a building can be classified as class I, II or III. If the approximate cost to build a building of a particular class in a given locality is known the total cost of the building, can be estimated on an area basis. In this article, we will examine the various components of the cost of the building so that we can control the cost during the execution stage itself. Charges for supervision and the supply of labour and materials which are paid for by the owner are usually taken as 7 to 10% of the overall cost of the building. In lump sum and item-wise contracts, because of the new tax laws, contractors expect a profit of 15 to 20% of the cost of the work.
BREAK UP OF COST OF
CONSTRUCTION
The table below gives the approximate average
percentage cost of civil works for a residential building. It also
indicates the possible savings that can be made. The actual values will depend
on many factors like foundation condition and architectural features.
Table: Percentage cost of civil works
S.No. |
Works |
Cost (% of the total
cost) |
Possible savings (% of the total
cost) |
1. |
Foundation and plinth |
10 to 15 |
1 to 3 |
2. |
Superstructure |
|
|
|
(wall + roof, including plastering) |
30 to 40 |
4 to 13 |
3. |
Painting |
5 to 20 |
1 to 8 |
4. |
Doors and windows |
12 to 20 |
1 to 8 |
5. |
Flooring |
10 to 20 |
2 to 7 |
In
addition, the cost of services is usually estimated as a percentage of civil
works and is taken as follows:
Water supply and sanitation |
10 to 12.5 per cent |
Electrical works |
8 to 12.5 per cent |
External works |
2 to 5 per cent |
Total |
20 to 30.0 per
cent (max) |
RATIO OF COST OF
MATERIALS TO LABOUR
It
has been found that the total cost can be divided
into the following percentages for
an ordinary building built in India in the traditional way:
1. Material cost - 60 per cent of the
total cost
2. Labour cost - 30 per cent of the
total cost
3. Other costs - 10 per cent of the
total cost
The
break up of the cost of materials can be approximated as given in the Tables below
Cost of principal materials
S.no |
Item |
Approximate cost
as % cost of the civil work |
1. |
Bricks |
15 to 18 |
2. |
Cement |
12 to 18 |
3. |
Steel |
5 to 15 |
4. |
Timber |
10 to 15 |
5. |
Sand |
7 to 10 |
6. |
Aggregate |
8 to 10 |
7. |
Paint |
5 to 10 |
Cost of labour
S.no |
Worker |
Approximate cost
as % of civil works |
1. |
Mason |
12 |
2. |
Unskilled labour |
12 |
3. |
Carpenter |
6 |
CONSUMPTION OF MATERIALS
FOR BUILDINGS
The
data given in the Table below can be taken as very approximate quantities of materials required for construction of an ordinary
building.
Table: Very approximate quantities of
materials required for a 1 m2 plinth area
S.No. |
Materials |
Quantity per m2
of plinth area |
1. |
Bricks
(9" ordinary) |
250-300
nos. |
2. |
Sand |
0.5
to 0.7 m3 |
3. |
40
mm aggregates |
0.2
m3 |
4. |
20
mm aggregates |
0.2
m3 |
5. |
Steel
for buildings with load bearing walls |
10
to 20 kg |
6. |
Steel
for framed flats and hostels |
30
to 50 kg |
7. |
Steel
for framed offices |
40
to 70 kg |
8. |
Cement
for load bearing walls |
3
bags |
9. |
Cement
for framed buildings |
4
bags |
10. |
Lime
for brick jelly |
40
litres |
ANALYSIS OF ITEMS OF
WORKS
The
quantities of important items of work
for buildings can be worked out to control cost as shown in the Table below
which is for a middle-class building
on load bearing walls. The values shown are not exact but only indicative.
Table: Items of works for residential buildings on
load-bearing walls (Quantitative are only indicative. Actuals will depend on
the design.)
s.no |
Materials |
Approximate
quantity per m2 of the plinth area |
|
G.F ONLY |
G.F + F.F |
||
1 |
Earthwork |
0.52 m3 |
0.30 m3 |
2 |
Mass concrete in foundation and under
floor |
0.22 m3 |
0.15 m3 |
3 |
RCC in foundation |
0.11 m3 |
0.06 m3 |
4 |
Brickwork in foundation (varies) |
0.16 m3 |
0.09 m3 |
5 |
Brickwork in superstructure |
0.40 m3 |
0.40 m3 |
6 |
RCC in superstructure: |
|
|
Plinth/lintel/beam |
0.05 m3 |
0.05 m3 |
|
Slab and stairs |
0.01 m3 |
0.18 m3 |
|
Sunshade/shelves |
0.18 m3 |
0.01 m3 |
|
7 |
Doors and windows |
0.45 m3 |
0.45 m3 |
8 |
Plaster |
2.60 m3 |
2.60 m3 |
9 |
Painting of walls and ceiling |
3.5 m3 |
3.5 m3 |
10 |
Waterproofing |
0.98 m3 |
0.60 m3 |
11 |
Flooring |
0.75 m3 |
0.75 m3 |
CEMENT REQUIREMENTS IN
CEMENT WORKS
Cement
is an important material and its consumption must be controlled. Some of
the data used for the calculation of cement requirements in concrete, mortar and
plaster are given in the Tables below
Table: Cement consumption for concrete
Mix |
W/c ratio |
Strength |
Cement per (m3
of concrete (kg) |
|
With control |
Without control |
|||
1 :1.5: 3 |
0.42 |
20 |
30 |
405 |
1 : 2 : 4 |
0.55 |
15 |
25 |
310 |
1 : 3 : 6 |
0.75 |
10 |
15 |
215 |
1 : 4 : 8 |
Used only for base concrete, etc. |
160 |
||
1 : 5 : 10 |
Used only for base concrete, etc. |
130 |
Note:
1 cubic metre = 35.315 cubic feet; Approximate yield = 2/3 x Volume of mix.
Hence, volume of cement required per m3 of concrete is taken as (1.52/ Volume of mix) (approx).
Table: Requirements for 1 m3
of cement mortar
Mix of mortar |
Cement (bags) |
Sand (m3) |
1:3 |
2.6 |
0.267 |
1:4 |
1.9 |
0.275 |
1:6 |
1.4 |
0.299 |
1:8 |
1.1 |
0.308 |
Note:
For brick masonry, we need 500 metric
bricks (and 520 ordinary bricks) per cubic metre of brickwork and 25 to 30% of the volume of brickwork
will be taken up by a mortar. Hence, we need about 0.25 to 0.30 cft of mortar. One bag of cement is considered as 50
kg in weight and 35 litres in volume.
Table: Requirements for 100 m2
of 12 mm thick cement plaster
Mix |
Cement
(bags) |
Sand
(m3) |
1 : 2 |
21 |
1.4 |
1 : 3 |
15 |
1.5 |
1 : 4 |
12 |
1.6 |
1 : 6 |
9 |
1.8 |
Note:
1 square metre = 10.764 square feet
ESTIMATION OF STEEL IN RC
WORKS
For preliminary estimation, it is usual to assume the steel requirement on a percentage basis (or kg/m3)
of the easily calculable volume of concrete based on the data given in Table below.
The actual requirement by proper design will be much less.
(Note: Steel rods usually come in
lengths of 11 m. Hence we can check the weight of a consignment by counting the
rods. For example, the weight of a consignment consisting of 8 rods each of length 11 m = 11 x 0.395 =
4.4 kg, approximately.)
Table: Estimation of steel in buildings
components (Fe 415 steel)
Item |
Coefficients
for estimation of steel |
|
As
% of steel |
As
Kg/m3 |
|
Footings |
0.25 to 0.65 |
20 to 50 |
Cast In-situ Piles |
0.40 to 0.75 |
30 to 60 |
Rafts |
0.75 to 1.50 |
60 to 120 |
Columns |
1.00 to 4.0 |
80 to 320 |
Beams |
0.5 to 1.5 |
30 to 100 |
Slabs and lintels |
0.3 to 0.6 |
25 to 50 |
Sunshades |
0.3 to 0.5 |
25 to 30 |
Note:
1% steel = 78.5 (say 80 kg) of steel per cubic metre of concrete.
Example: Find the steel required for a slab 15 x 10 m and 120 mm
thick.
Volume of concrete = 15 x 10 x 0.12 = 18 m3
Assume % of steel is 0.4 % = (or 0.4 x 78.5 = 31 kg/m3)
Wt of steel = 18 x 31 = 565 kg
(Note: This works out to 565 ÷ 150 =
3.76 kg/m2 for slab only. In addition we have foundation beams, columns etc. so
that the total quantity will workout to 10 to 20 kg/m2)
TYPICAL MINIMUM
CONSUMPTION
The
minimum consumption of steel in kg/m2
by proper design and detailing for a typical four storey building on good
soil using to Fe 415 steel can be a
total of 20 kg/m2 as
follows
Minimum steel for a four-storey flat
ITEM |
STEEL
CONSUMPTION |
Foundation |
2.0 kg/m2 |
Plinth beam |
2.0 kg/m2 |
Columns |
4.0 kg/m2 |
Beams |
5.0 kg/m2 |
Slabs and stairs |
5.5 kg/m2 |
Lintels, sunshade etc. |
1.5 kg/m2 |
ANALYSIS OF RATES
One
of the topics studied in "estimating"
is the analysis of the rates of various items of works. The data for the cost of
materials, labour and other items such as scaffolding required per unit of work
for each item of work in each region of the country is available. From these
data, the cost per unit of work can be estimated. As it is a subject to be studied underestimating, we will not go into
a detailed study of the subject in this article.
ESTIMATION OF PAINT
REQUIRED FOR PAINTING AN AVERAGE RESIDENTIAL BUILDING
(a) Rough estimate of areas to be
painted in terms of plinth area: Area of ceiling = Floor area (say plinth area)
Area
of internal walls = 3 x plinth area
Area
of external walls = 2 x plinth area
Area
of windows = 30% plinth area on each side
Area
of doors = 30% plinth area each side
(b) Approximate coverage of different
types of paints per coat (Second and third coats will have 25% more coverage).
1.
Fat lime for lime-washing 10 m2/kg
(For
colour wash add 1 to 2 kg colour per 100 m2)
2.
Dry distemper 10 m2/kg
3.
Cement paint 5 m2/kg
4.
Cement wall primer 8 m2/L (litre)
5.
Oil bound distemper 8 m2/kg
6.
Plastic emulsion paint 10 m2/L
7.
Acrylic exterior paint 12 m2/L
8.
Metal primer 10 m2/L
9.
Synthetic caramel paint 10 m2/L
10.
Copal varnish for wood 10 m2/L
MUST READ: Cost
Percentage Of Building Materials For 1000 Sqft of House Construction
MUST READ: Material
and labour Cost of One Room Construction | Room Estimation
FAQ
How Much Paint do I Need?
Example: Find the approximate quantity of paint required for
painting 200 m2 of wall with plastic emulsion paint in two coats.
Paint
required for first coat = (200/10) = 20.0 litres
Paint
required for second coat = 16.0 litres (10% less)
Total
= 36.0 litres (approx)
Note:
Generally one painter can be assumed to paint 15-20 m2 of wall
surface per day, depending on the type of paint and finish.
How much paint do I need for one coat?
Approximate coverage of different types
of paints per coat (Second and third coats will have 25% more coverage).
1.
Fat lime for lime-washing 10 m2/kg
(For
colour wash add 1 to 2 kg colour per 100 m2)
2.
Dry distemper 10 m2/kg
3.
Cement paint 5 m2/kg
4.
Cement wall primer 8 m2/L (litre)
5.
Oil bound distemper 8 m2/kg
6.
Plastic emulsion paint 10 m2/L
7.
Acrylic exterior paint 12 m2/L
8.
Metal primer 10 m2/L
9.
Synthetic cramel paint 10 m2/L
10.
Copal varnish for wood 10 m2/L
What is rate analysis?
One of the topics studied
in "estimating" is the analysis of the rates of various items of works.
The data for the cost of materials, labour and other items such as scaffolding
required per unit of work for each item of work in each region of the country
is available. From these data, the cost per unit of work can be estimated.
How many cement bags are used for
plastering?
Requirements for 100 m2 of
12 mm thick cement plaster
Mix |
Cement
(bags) |
Sand
(m3) |
1 : 2 |
21 |
1.4 |
1 : 3 |
15 |
1.5 |
1 : 4 |
12 |
1.6 |
1 : 6 |
9 |
1.8 |
Note:
1 square metre = 10.764 square feet
What is the percentage of cost of
materials and Labour?
1. Material cost - 60 per
cent of the total cost
2. Labour cost - 30 per
cent of the total cost
3. Other costs - 10 per
cent of the total cost
How much steel is in a building?
Estimation of steel in buildings
components (Fe 415 steel)
Item |
Coefficients
for estimation of steel |
|
As
% of steel |
As
Kg/m3 |
|
Footings |
0.25 to 0.65 |
20 to 50 |
Cast In-situ Piles |
0.40 to 0.75 |
30 to 60 |
Rafts |
0.75 to 1.50 |
60 to 120 |
Columns |
1.00 to 4.0 |
80 to 320 |
Beams |
0.5 to 1.5 |
30 to 100 |
Slabs and lintels |
0.3 to 0.6 |
25 to 50 |
Sunshades |
0.3 to 0.5 |
25 to 30 |
How to Calculate Construction Cost per Square Feet?
Thank you for help us to know the how the construction cost and material estimation cost will be for house. It is use full. Brainstorm Infotech is headquartered in Bengaluru, the start-up capital of India. It has carved a niche for itself in the field of structural steel detailing and allied services with a credit of completing over 1250 projects so far. We started small with a team of five professionals in 2010 but have earned the trust and respect of our clients that has led to long-standing associations.https://www.brainstorminfotech.co.in/
ReplyDelete